A Marble River Runs Through It
An earlier version of this article originally appeared in the Spring 2024 edition of Building Stone Magazine.

Just a few blocks from the White House, the building’s glass, terracotta, and metal facade seems to ripple like a waving flag. Photo by Jeff Goldberg/ESTO
When people engage with a beautifully designed place, they aren’t always aware of the myriad details that went into making it harmonious. They just know a space feels good to be in. They wouldn’t realize, for example, that when they wander through the lobby of 2100 Pennsylvania Avenue in Washington, D.C., they are walking on stone that underwent a complex dry lay at a fabricator’s facility in Turkey during the pandemic. Nor would they know the difficulties of creating curved walls or building solid cubic stone steps.
That is as it should be, and it’s a testament to the architect and stone installers who worked together through challenges to bring this Pinnacle Award-winning design in commercial interior to fruition.
HITTING THE RIGHT TONE
The project, which includes stonework for the lobby, back corridors, and upper penthouse, is part of a newly constructed building leased by George Washington University. The building sits on a V-shaped site, which Craig Copeland, FAIA, LEED AP BD+C, partner in charge at Pelli Clarke & Partners, wanted to take advantage of. He was inspired by Gaudi’s Casa Mila in Barcelona and the Flatiron Building in New York City for the design. “They both address the issue of approach,” he says. “At 2100 Penn,wewantedtomakesurethebuilding is reaching out like the prow of a boat but receiving you at the same time.”
The building’s exterior façade of glass, terracotta, and projected metal fins seems to undulate like an American flag—fitting since the building is about a five-minute walk from the White House. That movement and fluidity are carried inside. “The interior materials and their articulation play on metaphors of a natural sanctuary along a wooded stream,” says Copeland, a sculptor and product designer as well as an architect.
- Photo by Jeff Goldberg/ESTO
- Photo by Jeff Goldberg/ESTO
Copeland chose Turkish Dark Olive marble for the floors, steps, wall base, wall cladding, and coping — created from more than 1,000 cubic pieces of stone, which were eventually cut into more than 5,000 pieces. He visited the quarry in Turkey in 2018 and chose the marble for the material’s different tonalities, he says. “There are warm zinc and lead tones, ranging from very deep to very bright gray tones that we could achieve because of different finishes, high honed and leathered.”
In addition, he says, “from the start, I was thinking of also using wood and emulating the interior feel of a concert hall. I knew this Dark Olive marble, a sort of slate gray that sometimes looks chocolate, would be a nice complement to the warmth of the wood.”
CHALLENGES (DRY) LAID TO REST
Because of the size of the project, “the dry lay was done in stages,” says Lorton Stone’s Mauricio Benavides, vice president and chief estimator for the stone installer, who acted as project manager, adding that he’d “never seen this level of dry lay done before.” He accompanied the design team and the owner’s representative to the fabricators Silkar-AKDO, not far from the Dark Olive quarry in Sivas, Turkey. The group made four trips of about three days each to view the dry lay, one prior to the pandemic shutdown, two during, and one just as COVID-19 restrictions were lifting.
Benavides’ company had submitted shop drawings and fabrication tickets to the fabricator to let them know how many pieces of stone were needed. The entire project includes over 4,000 pieces of paving, with each piece eventually receiving a number.

The fabricators created temporary walls so the team could view the stone vertically, in its correct orientation. Benavides said he’d never seen this level of dry lay done before. The team spent nearly two weeks over the course of four visits to get the layout accurate. Photo courtesy Lorton Stone

Instead of separate steps and risers, the designers decided each stair would be full thickness, solid cubic stone. This way, veins could flow/transition seamlessly from the horizontal to vertical plane. The handrail pieces were water jet-cut for a perfect radial shape. With this “snake of a shape we had no tolerance for error. Our layout was very complicated,” Benevidas says. Photo courtesy Lorton Stone
The paving project began here at the base of the steps. It’s the control point, Benevidas says, the benchmark from which the installers pull dimensions. Installers drew on the concrete to lay out the pattern. Creating the marble ramp along the right side was particularly challenging as it twists, rises, and curves. Photo courtesy Lorton Stone
During the dry lay, Copeland and his team shuffled stones to find the right blend of shade, veining, and patterns. How designers determine veining is based on context, where the stones will be used. “We have a large area of stone on the penthouse,” he says. “It’s an intimate area and can handle finer veins. A grander area like the lobby wants larger veins and more expression, or the veins get lost and blended away. When you work with natural materials you want to showcase their qualities like veins and color. That’s the advantage of visiting a quarry. You can see the effect of these grand gestures. This is also why a dry lay is so invaluable. At 2100 Penn, balconies overlook the space, and you can see the movement of the whole floor.”
In addition to the floor dry lay, the fabricators built temporary wooden wall structures. “Everything was dry lay in its orientation,” Copeland says. “The walls had to be built so we could review the stones vertically.” They looked for ways to create as many repetitive panels as possible. The attention to detail on the dry lay enabled them to preview lippage problems. “We saw where we’d need to grind out lippage by hand and sandblast during the install,” Benavides says.
Once the dry lay was complete and the stones individually numbered, they were packed on palettes and shipped to the United States in containers. While building construction began in 2019, it was not yet completed when the stone arrived. “Even the windows hadn’t been installed,” Benavides says. “We had to go in first because there was no way to get the material into the building. The freight elevators weren’t even working.” They craned in material and started the installation on a bare concrete slab, first laying down about a three-inch bed of mortar with wire mesh and a bond coat.
Elements other than the floor also posed challenges. The steps are one example. They were originally designed as individual tread and separate riser, but the design team wanted them to appear as one piece. The steps are full thickness, solid cubic stone, with each tread weighing about 360 pounds.

The paving project began here at the base of the steps. It’s the control point, Benevidas says, the benchmark from which the installers pull dimensions. Installers drew on the concrete to lay out the pattern. Creating the marble ramp along the right side was particularly challenging as it twists, rises, and curves. Photo courtesy Lorton Stone
Turning blocks of stone into curved elements such as the round radial reception desk also added challenges. “No money was spared on fabrication,” Benavides says. The fabricator took a wire saw to a massive block of marble to create the curved piece making sure the face and the back follow nearly the same radius and a consistent thickness, meaning that both the front and back of the stone panel had to be wire cut. “Anywhere there’s a curve that’s radial on the front or back side there’s a danger that the piece will break. We didn’t have the room for these pieces to be more than about 1 1⁄4” thick,” Benavides says.

This cutaway offers a way to engage with the full scope of the building. The marble-paved stone and stairs rise from a three-story lobby into a ten-story atrium where filtered daylight invigorates the heart of the building. Rendering by Pelli Clarke & Partners
COMMUNITY ASSET
Completed in 2022, 2100 Penn is now home to cafes, offices, and shops as well as a bookstore with event space for readings and lectures. The interior appears almost as two separate buildings with the three-story marble-floored lobby connecting them. It’s like a river between two hills. Set just at the edge of GWU’s campus, the building serves more than just that community. It’s a bright, open space crisscrossed by the public, who stop to rest on stone benches, meander up walkways, knowing only that the space feels warm, expansive, and inviting. Says Copeland, “2100 Pennsylvania Avenue’s waving forms and natural materials infuse stronger connections with nature into the heart of the urban Foggy Bottom neighborhood.”